Implementing "TV Minor Modifications" Prior to Permit Revision
In accordance with 15A NCAC 2Q .0515, Title V permittees may make changes to their facility prior to receiving a revised permit if the following four (4) conditions are met:
1. | The change is a "minor modification" under 15A NCAC 2Q .0515 and does not revise any state-enforceable only portion of the permit. Minor modifications which qualify for implementation prior to permit revision are changes that:
|
2. | The permittee submits a complete Title V permit application. Complete applications include:
|
3. | The permittee has received an acknowledgment letter that the application is complete. (Completeness determination letters will be sent within 10 business days of receipt of a complete application.) |
4. | The Permittee follows the proposed interim permit terms and conditions and any other applicable requirements governing the change(s) until the DAQ takes final action on the application. |

The applicant assumes all financial risks associated with construction and operation without a permit revision.